In midsummer, the sun is hot, Jilin Petrochemical's annual 800,000-ton hydrocarbon reorganization project is being splashed on site, and employees are struggling to sprint to the general goal of the project. Up to now, the project has completed 85% of the total construction, and the rate of realization of nodes and the passing rate of quality have all reached more than 97%. It is expected that China Communications will be realized by the end of July.
The 800,000-ton-year hydrocarbon reorganization unit is an auxiliary project for the company's 10 million-ton oil refinery expansion project. After completion and production, it will increase the yield of oil refining products, promote the upgrading of product quality, and provide protection for Jilin Petrochemical's 10 million-tonne oil refining to a new level. .
Up to now, the project has completed 23,300 cubic meters of earth and stone, completed 100% of the total; prefabricated steel structure 878 tons, completed 100% of the total; 87 sets of equipment installed to complete the total 92.6%; laying process pipelines 11,864 meters , to complete 80.7% of the total.
Retractable Ceiling Fan,Retractable Blade Ceiling Fan,Retractable Fan,Retractable Fan Light
ZHONGSHAN UFAN ELECTRIC APPLIANCE CO. LTD , https://www.ufanelectric.com