With the completion of the renovation project of Anqing Petrochemical's 300,000-ton/year gas fractionation unit in the remote area and the completion of the project, the Department of Refining assumes the double responsibility of the safety production of each unit and the start of the new plant. Since the old I gas fractionation unit is currently under normal production, and the new I gas fractionation unit is under operation, the contradiction between the shortage of gas separation unit personnel is very prominent. In response, Refining One promoted the spirit of solidarity and collaboration, and deployed elite troops from catalysis, decompression, cracking, and other devices, and used the staff's large time to support the start of the gas separation plant.
After the new gas separation plant was handed over, the Department immediately flushed the device into water to remove system debris and open up the system piping to ensure the system was free. From April 21st on, the new air distribution unit began to enter the airtight experimental stage. All walks of life adhered to the site day and night, and gradually increased their pressure according to the operational requirements to check whether the valves, manhole welding, and installation were in good condition and eliminate the run in time. , take, drop, leak. Wang Yiting, a senior technician of the catalytic device, was on vacation. However, when he learned that the start-up of the new gas separation plant required human support, he volunteered and put in tight gas-tight experiments.
During the airtight process, some of the flanges were in a low position, and the airtight test was very difficult. Everyone climbed on the ground, kept changing observation angles, carefully checked and carefully checked; some of the flanges were in a high position and everyone contacted the equipment immediately. Technicians, scaffolding and then work hard. For several consecutive days, everyone reported the leaked items to the equipment technicians. After timely processing, the airtight inspections were conducted again to create favorable conditions for the start of the new gas separation plant.
Construction Hoist parts including Construction Hoist Mast Section , passenger hoist wall tie, Passenger Hoist Cage and other Hoist Steel Structure Parts. Construction Hoist Safety Device and Hoist Electrical Parts . BQ's construction hoist has the same design with Gjj construction hoist.
Some common spare parts for a passenger hoist include:
1. Wire Rope : Used for lifting and lowering the hoist cage.
2. Safety devices: Including limit switches, overload sensors, and emergency stop buttons.
3. Electric motor: Powers the hoist system.
4. Brake system: Ensures the hoist cage remains stationary when not in use.
5. Control panel: Controls the operation of the hoist, including the direction and speed of movement.
6. Gearbox: Transfers power from the motor to the wire ropes.
7. Bearings: Used to reduce friction and ensure smooth operation.
8. Electrical components: Such as relays, contactors, and fuses.
9. Hoist ropes: Used for manual operation or as a backup for the wire ropes.
10. Cabin doors: Including door rollers, hinges, and locks.
It is important to consult the manufacturer or a professional technician to ensure you purchase the correct spare parts for your specific passenger hoist model.
Construction Hoist Mast,Construction Hoist Spare Parts,Construction Building Hoist,Construction Elevator,Safety Device
SHEN YANG BAOQUAN BUSINESS CO., LTD , https://www.sytopkittowercrane.com